Crews working for WSSC will be in University Park starting on or about July 30, 2018 until March 2020 replacing our aging pipes as part of an infrastructure renewal program. Construction will replace approximately 3.3 miles of WSSC water main. Click on additional info to read the schedule of work and when you can expect them in your area, read the letter from WSSC and view a phase map.
In order to minimize the heavy truck traffic throughout the Town, heavy duty construction vehicles will be permitted to enter the Town using the emergency access at the Queens Chapel Road/Baltimore Avenue intersection for the duration of the project.
If you have any questions, contact Public Works Director Mickey Beall at 301-927-4262.
WSSC Contacts:
On-Site WSSC Inspector Theron Blount 240-469-4692 and Email
WSSC Technical Contract Supervisor Collins Njoku 301-206-4225 and Email
In case of a water or sewer emergency, contact WSSC's 24-hour Emergency Call Center at 301-206-4002.